County Commissioners approve a $2.1 million construction bid

information released

Last week, commissioners awarded a $2.1 million construction bid for Phase 1 of the Totem Pole Road improvement project in Manson.

LaRiviere Inc. of Rathdrum, Idaho, was the lowest of six bids on the project. The bid was 23 percent below the Chelan County engineer’s estimate.

Totem Pole Road is a road improvement project that has been in the works for several years. The first phase is from South Harris Avenue to Green Avenue. Construction may start as early as next month. The County will post the start date on their project website as soon as it is set.

Work includes:

  • A new stormwater treatment system with an outfall at Lake Chelan
  • Addition of sidewalk and curb and gutter
  • Rebuilding the intersection at Green Avenue and Totem Pole Road

Project Description

This road project ranks as the top capital improvement priority for Chelan County Public Works, aside from its bridge reconstruction projects, as listed in the 2017 Chelan County Transportation Element.

The project has been divided into two phases. Phase I will include improving the existing drainage and making new safety improvements on the lower section of the project.

Phase I construction is scheduled to begin in spring 2026. The drainage network will be reconstructed from Lake Chelan (near Pedoi Street) and north up Harris Avenue. Totem Pole Road will also be widened from Main Street to Furey Street, to include wider shoulders and sidewalks. The roadway will be widened from 18 feet to 28 feet in width.

Phase II of the project is dependant on the securing of funds; Phase II is a priority project that is included in the County’s Six Year Transportation Program (TIP). It will include further road safety improvements north of Furey Street and connect to the Mason School District. This second phase is currently unfunded, but some preliminary design work has been initiated. The county plans on doing a more in-depth study of traffic circulation to best meet the needs of road users. Additional public input will be incorporated before moving forward.