During the next couple weeks, there may be an occasional bridge closure or traffic interruption; the only one known at this time is for Thursday, May 30. One side of the bridge will continue to remain open for pedestrians and bicyclists at all times.
 
Activities planned for May 29 – June 5 
  • Finish up landscaping
  • Install handrail in Landing Park
  • Bridge rail repairs as needed
  • Stripe the roadway
  • Install traffic signs
  • Final touchups
After bridge repairs are completed the first week in June, there will be a 30-day wait prior to painting, which will complete the project.