WSDOT North Central Region Weekly Construction Update & Travel Advisory
Information released by WSDOT
On Wednesday (10/23), WSDOT and Washington State Parks are partnering on an open house to share a night of discussion regarding park improvements and active transportation improvement in the region.
Active projects for the week of October 21 – 25:
US 2 Washout Repair (East Wenatchee)
County: Douglas Highway: US 2 Region: North Central
Location: MP 128.6 (North of junction with SR 28)
Description: A WSDOT maintenance crew will repair wash out and fix curbing behind the guardrail on US 2/97 just north of Blue Rock Estates Drive.
Work schedule: Wednesday only from 7 a.m. to 4 p.m. expect flagger controlled traffic with short delays. Work is weather dependent.
Contact: North Central Region Communications 509-667-2815
SR 17 Intersection Improvements #9454 (Moses Lake)
County: Grant Highway: SR 17 Region: North Central
Location: MP 51-54 (Moses Lake)
Description: Neppell Electrical is the contractor for this project that will install flashing warning beacons at six intersections on SR 17 in Moses Lake between the eastbound I-90 off ramp and Broadway Ave. Intersections include eastbound I-90 off ramp at SR 17, SR 17/Kittelson Rd., SR 17/Yonezawa Blvd., SR 17/Nelson Rd., SR 17/E. Wheeler Rd., and SR 17/Broadway Ave.
Work schedule: Monday – Friday from 6 a.m. to 6 p.m. expect, shoulder closures and lane closures on SR 17 at intersections between the I-90 eastbound off ramp to Broadway Ave. where the contractor is installing electrical conduit and foundations for the new “Prepare To Stop When Flashing” alert systems.
Contact: Project Engineer Brian Pearson 509-667-2880
SR 28/13th Avenue Roundabout (City of Quincy)
County: Grant Highway: SR 28 Region: North Central
Location: SR 28 MP 28 (intersection with 13th Avenue)
Description: The City of Quincy has contracted Tommer Construction to build a roundabout at the intersection of SR 28 and 13th Avenue.
Work schedule: Tuesday night beginning at 9 p.m. to 6 a.m. Wednesday morning, expect flagger controlled traffic with delays up to 10 minutes at the roundabout where the contractor is installing pavement markings. Work is weather dependent.
Contact: Project Manager Bernadette Donald or City Engineer Ariel Belino 509-787-3523
SR 28 Ephrata to Soap Lake Paving and ADA Compliance #9367
County: Grant Highway: SR 28 Region: North Central
Location: MP 44.5-53.0 (Ephrata to Soap Lake)
Description: In this $3.6 million project, Columbia Asphalt and Ready Mix crews are lowering utilities and updating deficient sidewalk curb ramps to meet ADA standards.
Work schedule: In Ephrata, on Monday from 7 a.m. to 5 p.m. expect flagger controlled traffic with some delays where the contractor is performing stripe removal and utility adjustments.
Contact: Project Engineer Jeff Deal 509-667-2886
SR 971 Hazard Tree Removal (Chelan)
County: Chelan Highway: SR 971 Region: North Central
Location: MP 12.6 (west of junction with US 97A)
Description: A WSDOT maintenance crew will remove a hazard tree on SR 971 (S. Lakeshore Rd.) betweem Bear Mountain Rd. and Scenic Ranch Ln.
Work schedule: Monday only from 8 a.m. to 3:30 p.m. expect flagger controlled traffic with short delays.
Contact: North Central Region Communications 509-667-2815
You can subscribe to get email messages for both our region traffic alerts and the construction alerts. Sign in with an email address or phone number for texts and you are automatically subscribed to the requested list.
To get WSDOT Eastern Washington Twitter feeds, go to and follow: @WSDOT_East.