Updates on the Old Bridge Restoration & Traffic Impacts

Information and Photos by LakeChelanNow, HDCA and City of Chelan

Final Update until the project resumes in early spring.

Updated 11/16/18:

This week the crew is finishing up their winter shutdown activities and will be off site before the end of the week. There will be no lanes closures.

Construction is expected to restart in March, but the start date is weather dependent. When spring construction resumes, activities will include construction of the Landing Parking retaining wall and handicap ramp, stormwater improvements, sidewalk widening, landscaping, and irrigation. The entire project is anticipated to be completed by the end of May if the weather cooperates.

According to Chelan Public Works Director, Jake Youngren, the project up to this point has gone well.  On the matter of the the replacement light stanchions, Youngren indicated there has been a bit of a delay in the re-casting process. That portion of the project is back on track and should be completed either late this winter or by the time work starts again on the project in March. If not completed this winter, temporary lighting will be installed, including perhaps the stringing of holiday lights.

The City would like to thank everyone for your cooperation this fall. Project updates will resume again in late winter, once the anticipated restart date is known.

Loni Rahm photo – taken 11-1-18

Update 11/2/18:

Bridge closure Monday the 5th thru Wednesday the 7th for paving

Next week (November 5 – 9): Favorable paving weather has led the contractor to adjust next week’s activities. The bridge will be closed from Monday at 7 a.m. until Wednesday at 7 p.m. to pave the bridge and the trench approaching both ends of the bridge. The contractor will also continue repairs under the bridge.
November 12 – 16: Complete preparations for winter shutdown, possible temporary lane closures.
Pedestrian access continues to remain open at all times with bicyclists using the same area to cross. For safety, bicyclists are asked to walk their bikes due to the limited space and compromised condition of the roadway.

Update: 10/27/18:

Last week, workers dug up a portion of Woodin Avenue to connect the new water lines. Construction representatives indicated that the BC MacDonalds’ owners and customers were “extremely gracious” about the inconvenience.

Loni Rahm photo, taken 10/26/18

Loni Rahm photo, taken 10/26/18

Next week (Oct 29 – Nov 2):

The bridge will be closed 8.am – 5 p.m. Monday (weather dependent) to pour sidewalks and on Thursday for bridge deck repairs. There will be periodic lane closures Tuesday, Wednesday and Friday. However, the plan is to have no lane closures from 3-5 p.m. on Wednesday, Halloween, so as not to impact trick-or-treaters. The contractor will also continue repairs under the bridge.

November 2 – 9:

This week, possible 8 a.m. – 5 p.m.bridge closures (weather dependent) for bridge deck membrane installation and paving. The contractor will also continue repairs under the bridge.
Pedestrian access continues to remain open at all times with bicyclists using the same area to cross. For safety, bicyclists are asked to walk their bikes due to the limited space and compromised condition of the roadway.

Related LakeChelanNow Stories

Bridge Construction Updates: September 4 through 17

Lighting Up the Old Bridge

Making Waves – Episode 22

October 22 Update:

The bridge will be closed Thursday and Friday to pour bridge sidewalks. Possible intermittent lane closures Monday, Tuesday, and Wednesday to connect the new water main, install reinforcing steel for the bridge sidewalks, and install the park retaining walls. The contractor will also be starting under the bridge repairs.

October 29 – November 2:

Possible bridge day time closures for deck repair. The contractor will be installing retaining walls in the park and preparing for paving.

Pedestrian access continues to remain open at all times with bicyclists using the same area to cross. For safety, bicyclists are asked to walk their bikes due to the limited space and compromised condition of the roadway.

Dennis Rahm photo taken 10/22/18

Contractors install filler to help strengthen the expanded concrete walkway on the old bridge. Concrete will be poured over the top of these foundation forms.

October 12 Update:

Traffic Alert: Contractor anticipates day closures during the next two weeks. Pedestrian access will continue to be open at all times with bikes using the same area to cross. Bicyclists are asked to walk their bikes.

Next week (October 15-19): Possible day time closures for the underground water installation, including new hydrants, branch pipes, and meters, as well as testing of the water main. The contractor will also be installing rebar in the bridge sidewalk for widening, continue upgrading the electrical under the bridge, and starting the park demolition so they can install the retaining wall.

October 22 – 26: Possible day time closures for utility work, including connecting the water main to the new hydrants, branch pipes, and meters. Bridge deck repair is also anticipated, along with installation of the retaining walls in the park.

Note: This two-week look ahead reflects what the contractor anticipates at this time. Weather and other circumstances can change construction crew activities and bridge access. Please visit the project website for additional information.

Dennis Rahm Photo taken 10/10/18

Dennis Rahm Photo taken 10/10/18